Critical Metals Takes 100% of Greenland's Tanbreez With $264.5M in Cash
The company targets first ore in late 2028 to early 2029, subject to permitting and financing. Operating permits are still pending, and Tanbreez is not yet producing.
Critical Metals ($CRML) said it now owns 100% of Greenland's Tanbreez rare earth project after completing its acquisition of European Lithium on Nov. 5, and reported about $264.5M in cash after the deal. The company plans to advance mine development in 2027 and targets first ore in late 2028 to early 2029, subject to permitting, financing and construction. CRML traded at $5.98, up 2.71%, at 10:12 a.m. ET.
How ownership reached 100%
| Date | Tanbreez ownership |
|---|---|
| Start of 2026 | 42% |
| April 17 | 92.5%, after Greenland approved the transfer of the final 50.5% |
| Nov. 5 | 100%, on completion of the European Lithium acquisition |
CEO Tony Sage said the company started 2026 owning 42% of Tanbreez and finishes it owning all of it. The merger issued 90,539,994 new shares at 0.045 per European Lithium share, and European Lithium is now a wholly owned subsidiary.
Share count and cash
- Shares outstanding. The company counts 194,219,631 ordinary shares. It excludes 45,536,338 shares held by European Lithium, which carry no voting, dividend or winding-up rights while it remains a wholly owned subsidiary.
- Register count. About 239.8 million shares are on the register. The company said some data providers may show a figure near 240 million until their feeds update, and Sage said the share count has caused confusion.
- Cash. Cash was about $264.5M immediately after completion, which the company puts at about $1.36 per outstanding share. It was $102.5M at June 30, before the merger. Project finance for mine construction remains a 2027 objective.
- Warrants. Replacement warrants over about 8.1 million shares vest if the 20-day VWAP reaches $10.92, $12.48, $14.04 or $15.60, depending on the class.
Tanbreez progress
- Permits. Greenland approved the Mining and Closure Plans, covering 19 elements through Sept. 8, 2050. Operating permits for environmental management, marine transport, health and safety, and mineral export and sales are still pending.
- Drilling. The 2026 program, completed in October, drilled 52 diamond holes totaling 8,385 meters.
- Refining. Test work reported on Sept. 16 showed more than 99% dissolution of eudialyte concentrate into 19 high-purity products.
- Concentrate grade. Refined concentrate reached 2.96% TREO in a March 31 update, which the company says is about 40% better than historical test work.
- Site work. Construction began in January on a storage and pilot plant facility in Qaqortoq.
Financing and partnerships
- U.S. Export-Import Bank. A previously issued, non-binding Letter of Interest covers up to $120M for Tanbreez. Management seeks to renew and possibly expand it.
- REalloys. A binding 15-year agreement signed May 21 covers up to 15% of annual Tanbreez concentrate, with priority on dysprosium- and terbium-rich volumes.
- Romania and Saudi Arabia. The proposed Romanian refinery venture with FPCU and the Saudi processing venture are both covered only by non-binding term sheets. The Saudi offtake would cover 25% of concentrate for the life of the mine.
- Ucore. An offtake of about 10% is at the term sheet or letter of intent stage.
Non-core assets
The company began a strategic review of non-core assets after retaining advisors in July. Options include a partnership, joint venture, sale, spin-out or continued development, decided asset by asset, and proceeds are intended for Tanbreez. The assets include stakes in ASX-listed CuFe, Moab Minerals and Helix Resources, a 14.8% interest in unlisted uranium explorer Pan African Niger, and about $21.5M of senior bank debt owed by Ukrainian titanium producer Velta.
The 2027 roadmap
- Studies. A definitive feasibility study is targeted for Q4 2027, with NIRAS engineering a 500,000 tonne-per-year operation. The company also plans an updated resource and replacement economic study, and says its March 2025 preliminary economic assessment has been superseded.
- Permits and offtake. Secure the operating permits and convert the Romania, Saudi Arabia and Ucore term sheets into binding agreements.
- Production. First ore is targeted for late 2028 to early 2029, subject to permitting, financing, engineering and construction. Tanbreez is not yet producing.
How CRML traded
| Critical Metals ($CRML) | Price |
|---|---|
| Nov. 11 open | $6.05 |
| Nov. 11 range at 10:12 a.m. ET | $5.87–$6.05 |
| Nov. 11 at 10:12 a.m. ET | $5.98 (+2.71%) |
The Canadian Mining Journal reported that CRML fell 15.38% in New York on Nov. 5 after the new shares were issued.
What to watch
- Operating permits. Whether Greenland grants the four pending permits, which the company lists as a 2027 objective.
- Financing. Whether the EXIM indication is renewed or expanded, and whether project finance for construction comes together in 2027.
- Binding offtake. Whether the Romania, Saudi Arabia and Ucore term sheets become definitive agreements.
This article is informational only and is not investment advice.
Readers also read
FlexGen to Integrate Eos Zinc Storage at MN8's Mammoth Solar Project
NewsNscale's $35B IPO Hopes Strain as Microsoft Exits Essex and Investors Push Lower
RecapNasdaq Falls 4.4% and VIX Jumps 45% as Chip Stocks Plunge on Data Center Worries
NewsIran Security Chief Warns of Strikes on Distant U.S. Bases, Keeps Hormuz Shut
MarketCatalyst is not a registered investment advisor and does not manage client assets. Content on this platform is provided for informational and educational purposes only. It is not investment advice, and MarketCatalyst is not a stock-picking or trade-alert service. Trading stocks and options involves risk, including the possible loss of principal. Consider your own goals, time horizon, and risk tolerance, and consult a qualified financial advisor before making any investment decision.